An "Main Equipment Supply Agreement" was signed with Metso Finland Oy, a company based abroad, for the Yenipazar Project, with a total contract value of EUR 25.2 million. Under the agreement, the supply of the main machinery, equipment, and analyzers required for the crushing, grinding, flotation, and treatment sections of the flotation plant, which has commenced construction within the scope of the project, is planned.
According to the signed agreement, the estimated delivery periods for the equipment to be supplied vary between 7 and 12 months, depending on the nature of the equipment.